Change order form
Free template · AIA-styled

Change order form for general contractors

Use it once the owner, contractor and architect agree on a change to the work. Signing it confirms every term - including any change to the contract sum and the contract time.

Amends the prime contract
Changes the owner–contractor agreement, not a subcontract.
Use it when all parties agree
Owner, contractor and architect have settled the terms of the change.

Get the template

Free to download. Fill in your details to get the form.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Prime contract

Change Order

Change order no.
014
1
Contract and change
Project
Riverside Medical Centre
Owner
Riverside Health Trust
Date
Mar 12, 2027
Contractor
Tremblay Construction Ltd.
Architect
Hollis + Ward Architects
Contract date
Jun 3, 2026
The contract is changed as follows
Revise stair core formwork to suit modified geometry per Architect’s Drawing A5.3 Rev A, including layout, mock-up and temporary supports.
2
Contract sum
Original contract sum
$4,750,000.00
Net change by previous change orders
$118,400.00
Contract sum prior to this change order
$4,868,400.00
Increased by this change order
+$42,300.00
New contract sum, including this change order
$4,910,700.00
3
Contract time
Changed by this order
+5 days
Substantial completion, before
Aug 26, 2027
Substantial completion, now
Aug 31, 2027
4
Signed by all three parties
Architect
Signature · date
Contractor
Signature · date
Owner
Signature · date
Illustrative example · sample figures
What’s on the form

One sheet. Every term the three signers agree to.

1
Contract and change
Project, parties and dates, plus a plain description of the change to the work.
2
Contract sum
Original sum, prior changes, this change and the new contract sum in one column.
3
Contract time
Days added or removed and the revised substantial completion date.
4
Three signatures
Architect, contractor and owner sign. Once signed, the change is binding.