Resources
/
/
RFI template
Free template · AIA-styled · Word, Excel, PDF

Free construction RFI template

A construction RFI template turns a field question into a formal record. The contractor sends the RFI to the architect, engineer, or owner. The written response keeps the project moving and documents the decision.

Formats
Word
.docx
Excel
.xlsx
PDF
fillable
Google Docs
Resolves design conflicts before work proceeds
An RFI clarifies drawings, specifications, and site conditions.
Works for any party and any project size
The owner, architect, or contractor can initiate the RFI.

Get the RFI template

The template downloads in Word, Excel, and PDF. Fill in your details to get the files.

Thanks. Your RFI template download is starting.
Oops! Something went wrong while submitting the form.
AIA-styled · construction

Request for Information

RFI no.
014
1
Project and parties
Project
Riverside Medical Centre
Date issued
Mar 12, 2027
Response required by
Mar 19, 2027
To
Hollis + Ward Architects
From
Tremblay Construction Ltd.
Ball in court
Architect
2
Reference and question
Drawing A-520 · Detail 4
Drawing S-401
Spec 08 44 13 · Curtain wall
Question
Structural drawing S-401 shows embed plates for the curtain wall at Grid B4. Architectural detail A-520 shows a different anchor. Which detail governs the curtain wall anchors?
Suggested solution
Use the S-401 embed plates. The architect confirms the anchor spacing in a revised detail.
3
Cost and schedule impact
Cost impact
None
✓
Possible
Confirmed
Schedule impact
None
✓
Possible · +2 days
4
Response
Answered by the architect or engineer of record
5
Signatures
Requested by · Contractor
Signature · date
Responded by · Architect
Signature · date
Illustrative example · sample project and figures
What the template includes

Five fields. One written answer.

1
Project and parties
The header names the project, the sender, the recipient, and the response date.
2
Reference and question
The reference ties one question to a drawing, a detail, or a spec section.
3
Cost and schedule impact
The impact boxes flag potential change orders before work proceeds.
4
Response
The architect or engineer answers in writing on the same form.
5
Signatures
Two signatures close the RFI and complete the project record.
Sending more than a few RFIs a week? Buildend logs every RFI with its ball in court, due date, and impact.
See RFI management in Buildend →
How to write an RFI

A clear RFI gets a fast answer.

A well-written RFI asks one question, cites one location, and sets one deadline. These four steps fill every field on the template.

01

Check the documents first

The contract documents answer most questions. An RFI asks only what the drawings and specs leave unclear.

02

Ask one question

One question produces one answer. Bundled questions slow the design team’s response.

03

Cite the exact location

The sheet number, detail, grid line, and spec section locate the issue for the reviewer.

04

Set a response date

The required-by date protects the schedule. The contract defines the allowed response time.

An RFI is not a change order.

An RFI requests information. A change order modifies the contract sum or the contract time. A flagged RFI often precedes a change order.

From template to RFI log

One template per question. One log for the project.

The template documents a single RFI. Buildend tracks every RFI on the project — ball in court, priority, due date, and cost or schedule impact — in one shared log.

See RFI management in Buildend →
Icon Tower / Request for Information (RFIs)
Create an RFI
17
Total RFIs
16
Open / pending
3
Overdue
27
Avg days to close
2
Cost flagged
1
Schedule flagged
RFI
Ball in court
Priority
Status
Impact
Due
RFI-014 · Curtain wall anchor detail at Grid B4
Architect
High
In Review (Architect)
Cost · Schedule
Overdue 6d
RFI-011 · Structural steel connection detail
Structural Engineer
Critical
In Review (Engineers)
Cost
Jan 29
RFI-012 · Duct clearance at storefront, Unit 4
Mechanical Engineer
Medium
In Review (Engineers)
—
Feb 03
RFI-009 · Slab edge embed spacing, Level 3
Project Manager
High
In Review
Schedule
Feb 05
RFI-007 · Fire-rated door hardware substitution
Architect
Medium
Answered
—
Closed
Buildend RFI log · illustrative mockup, demo project
FAQ

RFI template questions

What is an RFI in construction?

An RFI is a formal written question about the contract documents. The contractor sends the RFI to the architect, engineer, or owner. The written answer becomes part of the project record.

What does an RFI look like?

An RFI is a one-page form. The form contains an RFI number, the parties, a drawing or spec reference, the question, a suggested solution, and a response.

How do you write an RFI?

A good RFI asks one question, cites the exact sheet and detail, proposes a solution, and sets a response date.

What is the difference between an RFI, an RFP, and an RFQ?

In construction, an RFI requests clarification during a project. An RFP requests proposals from vendors. An RFQ requests prices for defined work.

Who can submit an RFI?

Any project party can submit an RFI. Contractors and subcontractors send most RFIs to the design team.

Is the RFI template free?

Yes. The Buildend RFI template is free in Word, Excel, PDF, and Google Docs formats.