Resources/Templates/Subcontractor pay application
Free template · G702-styled · Excel, Word, PDF

Subcontractor application for payment template

A subcontractor application for payment bills the general contractor for work completed in one billing period. The form totals the contract sum, the work completed and stored, retainage, and previous payments, then shows the current payment due.

Formats
Excel.xlsx
Word.docx
PDFfillable
Google Sheets

Bills the general contractor for one period

The summary sheet shows the contract sum to date and the current payment due.

Backs every dollar with a schedule of values

The continuation sheet tracks progress, stored materials, and retainage line by line.

Get the pay application template

Fill in your details to download the form.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Subcontractor · Progress billing
Application for Payment
Application no.
06
1
Contract and period
Project
Harbor Point Apartments, Tacoma, WA
To contractor
Northgate Builders Inc.
Period to
Oct 31, 2026
Subcontractor
Cascade Line Electric LLC
Subcontract
Div. 26 · Electrical
Application date
Nov 5, 2026
2
Contract summary
1 · Original contract sum
$486,000.00
2 · Net change by change orders
+$24,500.00
3 · Contract sum to date
$510,500.00
4 · Total completed and stored to date
$308,150.00
5 · Retainage, 5% of completed and stored
−$15,407.50
6 · Total earned less retainage
$292,742.50
7 · Less previous applications for payment
−$152,427.50
8 · Current payment due
$140,315.00
9 · Balance to finish, including retainage
$217,757.50
3
Change order summary
Additions
+$24,500.00
Deductions
$0.00
Net change
+$24,500.00
4
Certified and approved
Subcontractor
Signature · date
General contractor
Approved amount · date
Notary
If the contract requires it
Illustrative example · sample project and figures
What’s on the form

One summary. One continuation sheet. Every dollar tied to a line.

1

Contract and period

Project, parties, application number, and the billing period the application covers.

2

Contract summary

The contract sum, work completed and stored, retainage, and previous payments roll up to the current payment due.

3

Change order summary

Approved additions and deductions adjust the original subcontract sum.

4

Certification

The subcontractor certifies the work and payments. The general contractor approves the amount.

Collecting pay apps from more than a few subs? Buildend logs each application against the right commitment and cost code.

See pay applications in Buildend →
Continuation sheet · G703-styled

The schedule of values behind the number.

The continuation sheet breaks the subcontract into line items. Each line shows the scheduled value, work billed before, work this period, stored materials, and retainage. Column G feeds line 4 of the summary.

AItem
BDescription of work
CScheduled value
DFrom previous
EThis period
FMaterials stored
GCompleted and stored
G ÷ C%
HBalance to finish
IRetainage 5%
01
Mobilization and general conditions
$28,000.00
$28,000.00
$0.00
$0.00
$28,000.00
100%
$0.00
$1,400.00
02
Underground electrical and conduit
$64,500.00
$58,050.00
$6,450.00
$0.00
$64,500.00
100%
$0.00
$3,225.00
03
Rough-in, branch circuits
$186,000.00
$74,400.00
$55,800.00
$0.00
$130,200.00
70%
$55,800.00
$6,510.00
04
Switchgear and panelboards
$142,000.00
$0.00
$21,300.00
$56,800.00
$78,100.00
55%
$63,900.00
$3,905.00
05
Lighting fixtures and devices
$65,500.00
$0.00
$0.00
$0.00
$0.00
0%
$65,500.00
$0.00
06
CO-01 · EV chargers, level P2
$24,500.00
$0.00
$7,350.00
$0.00
$7,350.00
30%
$17,150.00
$367.50
Totals
$510,500.00
$160,450.00
$90,900.00
$56,800.00
$308,150.00
60%
$202,350.00
$15,407.50
Illustrative example · sample project and figures
How the numbers tie
G = D + E + F → summary line 4
I = G × 5% → summary line 5
Due = (E + F) × 95% → summary line 8
How to fill out a subcontractor pay application

Bill what the schedule of values shows.

A pay application gets approved fast when every number traces to a line item. Fill in the continuation sheet first, then let the totals carry to the summary.

01

Update the schedule of values

Enter the scheduled value for each line, including approved change orders. The total equals the contract sum to date.

02

Bill this period’s progress

Enter work completed this period and materials stored on site. Percent complete should match what the superintendent sees.

03

Apply retainage and prior payments

Withhold the retainage rate the subcontract sets. Subtract the amounts certified on earlier applications.

04

Certify, attach, and submit

Sign the certification and attach the lien waivers the GC requires. Submit before the monthly cutoff date the subcontract sets.

A pay application is not an invoice.

An invoice bills a fixed amount. A pay application bills progress against a contract and shows the GC what is earned, what is held back, and what is left to finish.

AIA G702S, ConsensusDocs 710, or a template

Use the form your subcontract names.

Some subcontracts require a specific pay application form. When the subcontract names none, this template covers the same summary and continuation lines.

AIA G702S
ConsensusDocs 710
Buildend template
Publisher
AIA Contract Documents
ConsensusDocs
Buildend
Cost
Paid AIA license
Paid ConsensusDocs subscription
Free
Best fit
Subcontracts written on AIA documents
Subcontracts written on ConsensusDocs
Any subcontract billed against a schedule of values
Formats
AIA online editor, PDF output
ConsensusDocs online platform
Excel, Word, PDF, Google Sheets
From template to pay app log

One template per sub. One log for every draw.

The template covers one subcontractor’s application. Buildend collects every sub’s pay app for the draw, with progress, stored materials, and retainage tied to the right commitment and cost code.

See pay application software in Buildend →
Harbor Point / Pay Applications · Draw 06
Export ▾
Request pay apps
12
Sub pay apps
8
Approved
3
In review
$1.24M
Billed this draw
5%
Retainage held
Nov 25
Owner draw due
Subcontractor · application
Cost code
Complete
Status
This period
Retainage
Cascade Line Electric · App 06
26-00-00 · Electrical
60%
In Review (PM)
$147,700.00
$7,385.00
Summit Mechanical · App 06
23-00-00 · HVAC
48%
Approved
$96,400.00
$4,820.00
Puget Sound Plumbing · App 05
22-00-00 · Plumbing
52%
In Review (PM)
$58,250.00
$2,912.50
Evergreen Interiors · App 03
09-21-00 · Drywall
22%
Submitted
$41,800.00
$2,090.00
Rainier Concrete · App 06
03-30-00 · Concrete
95%
Approved
$12,600.00
$630.00
Buildend pay application log · illustrative mockup, demo project
FAQ

Pay application template questions

What is a subcontractor application for payment?

A subcontractor application for payment is a progress bill. The subcontractor sends it to the general contractor each billing period. The application shows work completed against the schedule of values and the payment due.

What is the difference between a G702 and a G703?

The G702 is the summary sheet: contract sum, completed work, retainage, and current payment due. The G703 is the continuation sheet: the schedule of values, line by line. The two sheets work together.

How is retainage calculated on a pay application?

Retainage equals the retainage rate times the work completed and stored to date. At 5%, $308,150.00 of completed work holds back $15,407.50. The subcontract sets the rate. The construction retainage calculator checks the math.

Can a subcontractor bill for stored materials?

Many subcontracts allow billing for materials stored on site or at an approved location. The continuation sheet records stored materials in column F. The subcontract sets the conditions.

What documents go with a subcontractor pay application?

General contractors often request lien waivers, backup for stored materials, and certified payroll on public work. The subcontract lists the required attachments.

Is the subcontractor pay application template free?

Yes. The Buildend subcontractor pay application template is free to download.