How to Calculate Percentage of Work Completed in Construction (and Which Number to Trust)

Calculate percent complete with cost-to-cost and line by line on the schedule of values, then reconcile the gap before it reaches your WIP and over/under billing.

Field percent of 37.75% against cost-to-cost of 50% before reconciliation, and 37.75% against 37.5% after removing $400,000 of uninstalled switchgear

Your project manager says the job is 50% complete. The cost report says 50% too. Then you walk the electrical room and find a $400,000 switchgear package still crated on pallets. That cost is in the job, but none of it is installed, so the 50% claims work nobody has built yet.

That one percentage sets earned revenue, over or under billing, and the gross profit your surety, your bank and your auditors read every quarter. An overstated percentage books margin early. The correction lands later, usually as fade near the end of the job.

"If you are 90% of the way complete on cost and 40% of the way complete on labor hours and quantity, somebody overspent somewhere."

- Josh Bohlke, CFO of an electrical contractor, on the Finance at the Jobsite podcast

This guide shows how to calculate percentage of work completed in construction two ways: cost-to-cost from your accounting data, and line by line on the schedule of values from the field. It then gives you a check to reconcile the two numbers and turns the agreed figure into one WIP row you can defend. Every figure below is an illustrative example from one fictional $2.4 million commercial job.

Field percent of 37.75% against cost-to-cost of 50% before reconciliation, and 37.75% against 37.5% after removing $400,000 of uninstalled switchgear

How to calculate percentage of work completed in construction with cost-to-cost

Divide the cost incurred to date by the total estimated cost of the job, then multiply that percentage by the current contract value to get earned revenue. Both inputs come from your job costing records: cost to date from posted invoices and payroll, and total estimated cost from the current budget plus the PM's estimate to complete.

The illustrative job starts with these figures:

ItemIllustrative example
Current contract value$2,400,000
Total estimated cost$2,000,000
Cost incurred to date$1,000,000
Percent complete (cost-to-cost)$1,000,000 ÷ $2,000,000 = 50%
Earned revenue to date50% × $2,400,000 = $1,200,000
Gross profit to date$1,200,000 − $1,000,000 = $200,000

Cost-to-cost is the default because the inputs already sit in your accounting system. That convenience is also its weakness.

Where cost-to-cost overstates progress

Cost-to-cost treats every dollar spent as a dollar of work put in place. Five kinds of cost break that assumption:

  • Uninstalled materials. Equipment delivered to site but not set or connected.
  • Front-loaded subcontract costs. A sub bills heavily early, and its invoice lands in your cost to date.
  • Mobilization and setup. Real costs that build nothing permanent.
  • Change order costs outside the contract. The cost is in the job, but the contract value has not moved until the change order is executed.
  • A stale estimate to complete. The denominator still reflects the original bid.

The accounting standard addresses the first one directly. Under ASC 606-10-55-21, a contractor using a cost-based input method excludes costs that do not depict its performance, such as uninstalled materials that meet four stated conditions. On the illustrative job, $400,000 of the $1,000,000 cost to date is that crated switchgear. Accounting cannot see that from the cost report alone, so you need a second number that comes from the field.

Calculate percentage of work completed line by line on the schedule of values

Measure physical progress on each schedule of values (SOV) line with the method that fits that scope, weight each line by its scheduled value, and add the results. A single job-wide percentage hides which scope is ahead and which is behind.

"It's a one line, we are 50 % through with the project schedule of values. Well. That's a lot harder to verify than breaking it out by building, by level, by unit, by scope."

- Michael McKeon, Project Manager at Nordby Construction, on the Finance at the Jobsite podcast

Pick a measurement method for each line

Each method below fits a different kind of scope. Use the most objective method each line allows, and save supervisor estimates for lines too small to count.

Comparison of five percent-complete measurement methods: units installed, weighted milestones, start-finish, time elapsed and supervisor estimate, with how each works, where it fits and its weak point

Roll the lines up by value

The illustrative job's SOV, measured in the field, rolls up to $906,000 of earned value on a $2,400,000 contract, or 37.75%.

SOV roll-up of five lines weighted by value: general conditions 45%, concrete and structure 85%, electrical 20%, mechanical 30%, finishes 0%, totalling $906,000 or 37.75%

The field says 37.75%. Accounting says 50%. Electrical shows why: the switchgear milestone (25% of that line) earns nothing until the gear is set.

A 12-point gap is too large to sign. The next step is finding out where it comes from.

Reconcile field percent and cost percent before it goes on the WIP

Compare the two percentages every month, and trace any gap above your threshold to a specific cause before you choose which figure to report. The gap is information. Each cause points to a different correction.

"The final, most important number is percent complete. Is the job physically as complete as the numbers show?"

- Kevin O'Shea, President and CFO of Shamrock Electric, in CFMA's Member Two Cents column

Work through the check in this order:

  1. Set a review threshold. Review any job if the gap between field and cost percent exceeds a figure you choose, for example 5 percentage points.
  2. Remove uninstalled materials. Pull delivered but uninstalled equipment out of cost to date and total estimated cost.
  3. Check front-loaded lines. Compare each subcontractor's billed percentage with your field measure for that line, using the same review you apply to a subcontractor application for payment.
  4. Match change order costs to contract value. Costs incurred on unexecuted change orders inflate cost-to-cost without raising the contract. The change order cost impact calculator shows the effect on margin.
  5. Update the estimate to complete. Ask the PM for a current cost to complete, line by line, including open commitments.
  6. Audit cost coding. Miscoded invoices move cost between lines and jobs. Consistent construction cost codes keep each cost on the SOV line it belongs to.
Monthly reconciliation flowchart: if the gap between field and cost percent exceeds 5 points, check uninstalled materials, front-loaded lines, change orders, estimate to complete and cost coding, then rerun the check

On the illustrative job, step 2 closes the gap. Excluding the $400,000 switchgear from both the numerator and the denominator gives ($1,000,000 − $400,000) ÷ ($2,000,000 − $400,000) = 37.5%. If the switchgear meets the ASC 606 conditions, you recognize revenue equal to its cost at zero margin: 37.5% × ($2,400,000 − $400,000) + $400,000 = $1,150,000 earned. Cost now says 37.5% and the field says 37.75%. The two numbers agree, so you sign.

Step 5 is where most WIP reviews stall. CFOs report the same pattern on CFMA's member forum:

"A good portion of this is PM's sandbagging their projections."

- Mark Windham, CFO of Brasington Bailey Construction, on CFMA Connection Cafe

When the estimate to complete changes

Revise total estimated cost as soon as the PM's estimate changes, and book the cumulative effect in the current month. On the illustrative job, a $100,000 increase in estimated cost takes the adjusted percentage to $600,000 ÷ $1,700,000 = 35.3%. Earned revenue drops to $1,105,882, so this month absorbs a $44,118 reduction. A construction budget tracking routine that separates committed cost from actual cost catches these increases earlier.

If total estimated cost exceeds contract value, the job is a loss contract. Under ASC 605-35-25-45, you recognize the entire anticipated loss in the period it becomes evident.

Once you have a percentage you trust, it becomes the basis for the number your surety reads first.

Turn the percentage of work completed into earned revenue and over/under billing

Subtract earned revenue from billings to date: a positive result is overbilling (a liability), and a negative result is underbilling (an asset). The same sign convention runs down every row of a WIP schedule.

The illustrative job has billed $1,300,000. Correcting the percentage from 50% to 37.5% lowers earned revenue to $1,150,000, raises overbilling from $100,000 to $150,000 and cuts gross profit to date from $200,000 to $150,000.

WIP row before and after reconciliation: percent complete 50% to 37.5%, earned revenue $1,200,000 to $1,150,000, overbilling $100,000 to $150,000, gross profit to date $200,000 to $150,000

Sureties and banks read that overbilling line closely, because it sets the bonding capacity they extend.

"I have to meet every year with our underwriter from our bonding to go through jobs on the WIP and why did we lose or gain?"

- Jennifer Murphy, CFO of Pleune Service Company, on the Finance at the Jobsite podcast

For the pay application that follows from these numbers, see Buildend's construction progress payments example, and use the construction retainage calculator for the amount withheld.

Accounting and tax rules to confirm with your CPA

These rules shape how your percentage is used in financial statements and tax returns:

  • ASC 606 measures of progress. Output methods (such as units installed) and input methods (such as cost-to-cost) both measure work satisfied over time.
  • IRC §460 for tax. Long-term construction contracts default to the percentage-of-completion method. A contract expected to finish within two years is exempt if average annual gross receipts for the prior three years do not exceed $32,000,000 for tax years beginning in 2026, according to IRS Rev. Proc. 2025-32, section 4.30.

Getting one month right is useful. Getting every month right needs a routine.

Set up a monthly percent-complete review your team will keep

Run the same two-number check every month in one sheet, with a named owner for each input and an approver for every override. Consistency matters more than the method you choose.

Spreadsheet layout

Build one row per SOV line with these columns:

ColumnContentsFormula
ASOV lineText
BScheduled valueInput
CMeasurement methodText
DLine % complete (field)Input from PM
EEarned value (field)=B2*D2
FCost to dateFrom accounting
GUninstalled materials in costInput from PM
HEstimate to completeInput from PM
ILine % complete (cost)=(F2-G2)/(F2-G2+H2)
JGap=D2-I2
KReview flag=IF(ABS(J2)>0.05,"Review","")

Total field percent is =SUM(E:E)/SUM(B:B). Keep last month's sheet untouched so you can compare cumulative percentages month to month.

Spreadsheet layout with one row per SOV line showing field percent, cost to date, uninstalled materials, estimate to complete, cost percent and gap for the illustrative job

Who owns which number

Assign each input to one person:

  • Project manager: field percent per line, uninstalled materials and estimate to complete.
  • Accounting: cost to date, billings and the WIP close.
  • Operations leader: approval of any override above the threshold.

Override control is where spreadsheets break. Robin Thomas, Director of Project Accounting at The Beck Group, put the question to peers on CFMA's member forum: if operations can input overrides, "how is that information reviewed or approved with Accounting before the financials are closed?"

In a spreadsheet, the answer is often an email thread. Buildend's job costing separates actual costs, commitments and cost to complete for each cost code, and lets you configure approval workflows and permissions on financial records. Its payment application workflow reviews progress billing against the commitment in the same platform, inside Buildend's wider construction financial management software.

Your first step this month

Percent complete is two numbers. When you calculate percentage of work completed in construction from both the field and the cost report, the gap between them tells you what to fix before the WIP goes out.

Pick your three largest active jobs. For each one, have the PM measure every SOV line, pull cost-to-cost from accounting, and list any job where the gap exceeds 5 points. Trace each flagged gap through the six checks above before you sign.

If you want to see that review with your own data, bring one job's WIP to a Buildend demo and follow its percent complete, cost to complete and billing in one place.

See Buildend on a real workflow.
Book a demo ↗

See Buildend's Construction Management Platform in Action

Ready to experience firsthand how our construction management software can transform your projects? Request a demo now and discover the simplicity, efficiency, and control Buildend brings to your team.

Request a Demo